President Marcos On Chinese New Year: Seek Grand Ambitions For Greater Good

Sa pagdiriwang ng Chinese New Year, hinihimok ni Pangulong Marcos ang lahat na mangarap ng malaki para sa ikabubuti ng bayan.

Tourism Promotions Generate Record-High PHP11.3 Billion In Sales Lead

Tourism Promotions nagdala ng rekord na PHP11.3 bilyon na benta mula sa mga turismo noong nakaraang taon. Isang tagumpay para sa bansa.

New Facilities Improve Health Services In 8 BARMM Towns

Mga bagong pasilidad ang pinahusay ang serbisyong pangkalusugan sa 8 bayan sa BARMM. Isang hakbang patungo sa mas mabuting kalusugan para sa lahat.

WVSUMC Cancer Center Ready To Operate Full-Time

Ang WVSUMC Cancer Center ay handa nang mag-operate ng full-time, salamat sa karagdagang 52 tauhan.

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

The DPWH is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, which is now halfway done.
By The Philippine Post

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

0
0

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Department of Public Works and Highways (DPWH) is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, this province.

DPWH Pampanga 1st District Engineer Almer Miranda said on Wednesday that the rehabilitation, reconstruction, and upgrading of the 1,642 linear-meter Minalin section of the Manila North Road is now halfway done.

“We have been under strict instruction from Regional Director Roseller Tolentino to exhaust all means to expedite our projects months before the onset of the rainy season,” Miranda said in an official social media post.

The national government has allotted some PHP91 million for the rehabilitation of the damaged sections of Manila North Road that is being implemented through the DPWH’s Asset Preservation Program.

Miranda said the implementation of the rehabilitation project funded under General Appropriations Act for the year 2020 began on Dec. 1, 2020.

Although the project was tagged as under “For Later Release,” he said the Pampanga 1st District Engineering Office immediately started the road rehabilitation project after the Department of Budget and Management released the funds, making it 73 percent complete as of May 25, 2021.

“We are doing our best to meet the July 2021 target to complete the road rehabilitation. Three years ago, in 2019, the average daily traffic along this section of the Manila North Road is at 50,000, and considering this volume of vehicles that surely increased in three years, it is expected that the condition of the road pavement had to take the toll,” Miranda added. (PNA)