President Marcos Proud, Satisfied With 2024 Economic Feats

Proud si Pangulong Marcos sa tagumpay ng ekonomiya ng Pilipinas sa 2024. Kailangan nating ipaalam ito sa ating mga kababayan.

Secretary Recto Lures Investors At WEF To Locate In Philippines With CREATE MORE

Pinasisiya ni Secretary Recto ang mga global investors na tumingin sa Pilipinas bilang makabagong sentro ng negosyo sa World Economic Forum.

Over 7.2K Security Forces To Ensure Safety Of 2025 Dinagyang Festival

Mahigit 7,200 na puwersa ng seguridad ang nakatalaga para sa kaligtasan ng Dinagyang Festival 2025. Kahalagahan ng seguridad sa kultura.

Surigao Del Norte State University Students Receive PHP1.1 Million Aid

Surigao del Norte State University ng Claver Campus, nakatanggap ng PHP1.1 milyong tulong pinansyal mula sa gobyerno. 555 estudyante ang nakinabang.

Bridge Connecting Binondo, Intramuros 88% Complete

The Binondo-Intramuros Bridge is now 88.63% complete!
By The Philippine Post

Bridge Connecting Binondo, Intramuros 88% Complete

0
0

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Binondo-Intramuros Bridge is nearing completion, with the overall progress now at 88.63 percent, the Department of Public Works and Highways (DPWH) reported in a news release on Friday.

Undersecretary Emil Sadain reported to DPWH acting Secretary Roger Mercado that with the completed basket-handle tied steel arch main bridge over Pasig River, the target finish is by the first half of 2022.

The bridge was originally planned to open to motorists by the end of 2021 but the DPWH had to push back the timeframe to relocate public and private services and utilities in the area, as well as to wait for the pre-fabricated steel materials from China, which financed the PHP3.39 billion project.

Work suspensions due to the pandemic restrictions also affected the progress.

Sadain said the installation of pre-fabricated girders for abutments and ramps has begun while already lifted on piers are steel box girder components for the up-ramp at the Intramuros side with a total length of 191 meters and between Piers 5 and 8 for the viaduct structure over Estero de Binondo and corresponding ramp at the Binondo side.

“We are expecting a lot of dramatic changes for this project, with all the needed materials and high-performance launching equipment available on the construction site,” he said in a statement.

Considered one of the flagship infrastructure projects of the DPWH under the “Build, Build, Build” program, the bridge project is expected to not only cut travel time between the two busy districts of Intramuros and Binondo in Manila but also benefit about 30,000 vehicles daily.

The 680 linear-meter bridge will connect the historic district of Intramuros at Solana Street and Riverside Drive with bustling Binondo at Rentas Street/Plaza del Conde Street and Muelle dela Industria Street. (PNA)