President Marcos Proud, Satisfied With 2024 Economic Feats

Proud si Pangulong Marcos sa tagumpay ng ekonomiya ng Pilipinas sa 2024. Kailangan nating ipaalam ito sa ating mga kababayan.

Secretary Recto Lures Investors At WEF To Locate In Philippines With CREATE MORE

Pinasisiya ni Secretary Recto ang mga global investors na tumingin sa Pilipinas bilang makabagong sentro ng negosyo sa World Economic Forum.

Over 7.2K Security Forces To Ensure Safety Of 2025 Dinagyang Festival

Mahigit 7,200 na puwersa ng seguridad ang nakatalaga para sa kaligtasan ng Dinagyang Festival 2025. Kahalagahan ng seguridad sa kultura.

Surigao Del Norte State University Students Receive PHP1.1 Million Aid

Surigao del Norte State University ng Claver Campus, nakatanggap ng PHP1.1 milyong tulong pinansyal mula sa gobyerno. 555 estudyante ang nakinabang.

Cebu’s 3rd Bridge Now 87% Complete

The online registration for the installation of radio-frequency identification stickers has now started to pass Cebu’s third bridge.
By The Philippine Post

Cebu’s 3rd Bridge Now 87% Complete

33
33

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Cebu-Cordova Link Expressway Corp. (CCLEC) has started the online registration for the installation of RFID (radio-frequency identification) stickers, which motorists will need to pass Cebu’s third bridge that is set to be operational early next year.

The company announced on Tuesday that the construction progress of the 8.9-kilometer Cebu-Cordova Link Expressway (CCLEX) project was 87.14-percent complete as of end-October.

The PHP30-billion toll bridge project, which will be substantially completed by yearend, will use an all-electronic toll collection system when it opens in the first quarter of 2022 to provide motorists with safe and seamless travel.

Motorists may register for RFID through https://mptc.outsystemsenterprise.com/ORRAS/.

Topping the construction accomplishment is the completion of the CCLEX main bridge deck that connects Cebu City and the municipality of Cordova. Works have now moved to the construction of the deck’s safety barrier.

“Earlier, we have also finished the installation of all 56 stay cables holding the main bridge deck as well as the installation of all 434 NU (Nebraska University) girders required for the entire stretch of the project. Also completed is the 200-meter pedestrian footbridge. Work on the other segments of the CCLEX project continues to progress,” CCLEC said in a statement.

At the Cebu South Coastal Road (CSCR) on ramp and off ramp sections of CCLEX, ongoing now is the construction of the deck slab following the completion of its substructure and installation of precast planks.

At the Cebu viaduct, the construction of the deck slab is also ongoing. The Cordova viaduct, on the other hand, is now structurally complete and works are now on the construction of the safety barriers.

Aside from these, works are ongoing for the toll plaza, CCLEX Operations and Maintenance Center, and the Toll Operations Center building.

CCLEX is a project of CCLEC, in partnership with the local government units of Cebu City and Cordova.

CCLEC is a wholly-owned subsidiary of Metro Pacific Tollways Corp., the toll road arm of Metro Pacific Investments Corp. (PNA)