JT’s Manukan Grille Set To Spice Up Dubai’s Culinary Scene

Ang JT’s Manukan Grille, na kilala sa kanilang chicken inasal at iba pang Filipino specialties, ay magbubukas ng branch sa Dubai upang palawakin ang kanilang pandaigdigang presensya.

President Marcos Hopes Al Isra Wal Mi’raj Inspires Amity, Perseverance

Ang Al Isra Wal Mi'raj ay paalala sa atin na ang pagkakaisa at pagtutulungan ay susi sa tagumpay. Sumama tayo sa pagdiriwang na ito.

Kanlaon-Hardest Hit Town Marks Win At Dinagyang Festival’s Ilomination

La Castellana, na lubos na naapektuhan ng pagsabog ng Mt. Kanlaon, ay nagdiriwang ng tagumpay ng Tribu Bailes de Luces sa Dinagyang Festival.

PAGCOR, AFP Medical Center Unveil PHP53 Million Patient Watchers Dormitory

PAGCOR at AFP Medical Center, nagbukas ng PHP53 M na dormitoryo para sa mga pamilya at tagapag-alaga ng pasyente sa V. Luna Medical Center.

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

The DPWH is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, which is now halfway done.
By The Philippine Post

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

0
0

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Department of Public Works and Highways (DPWH) is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, this province.

DPWH Pampanga 1st District Engineer Almer Miranda said on Wednesday that the rehabilitation, reconstruction, and upgrading of the 1,642 linear-meter Minalin section of the Manila North Road is now halfway done.

“We have been under strict instruction from Regional Director Roseller Tolentino to exhaust all means to expedite our projects months before the onset of the rainy season,” Miranda said in an official social media post.

The national government has allotted some PHP91 million for the rehabilitation of the damaged sections of Manila North Road that is being implemented through the DPWH’s Asset Preservation Program.

Miranda said the implementation of the rehabilitation project funded under General Appropriations Act for the year 2020 began on Dec. 1, 2020.

Although the project was tagged as under “For Later Release,” he said the Pampanga 1st District Engineering Office immediately started the road rehabilitation project after the Department of Budget and Management released the funds, making it 73 percent complete as of May 25, 2021.

“We are doing our best to meet the July 2021 target to complete the road rehabilitation. Three years ago, in 2019, the average daily traffic along this section of the Manila North Road is at 50,000, and considering this volume of vehicles that surely increased in three years, it is expected that the condition of the road pavement had to take the toll,” Miranda added. (PNA)