PBBM To Filipinos Abroad: Exercise Your Right, Avail Of Online Voting

Ang mga Pilipinong nasa ibang bansa ay hinikayat ni Pangulong Marcos na gamitin ang kanilang karapatan sa pagboto sa pamamagitan ng Online Voting System.

DTI Chief: First Quarter GDP Growth Shows Resilient Philippine Economy

Ayon sa DTI, ang paglago ng GDP sa unang kwarter ng 2025 ay patunay ng katatagan ng ekonomiya ng Pilipinas sa harap ng mga pagsubok.

DAR Distributes PHP8.2 Million Equipment To Bukidnon Farmers’ Groups

DAR namahagi ng PHP8.2 milyong kagamitan sa 15 agrarian reform beneficiary organizations sa Bukidnon, pinatatag ang sektor ng agrikultura.

Iloilo City Launches 1st LGU-Led Nutrition Hub For Kids, Moms

Iloilo City inilunsad ang unang LGU-led Nutrition Hub para sa mga bata at mga ina. Ang Uswag Nutrition Center ay naglalayong magbigay ng masustansyang pagkain para sa lahat.

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

The DPWH is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, which is now halfway done.

DPWH Hastens Rehab Of Manila North Road’s Damaged Sections

0
0

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The Department of Public Works and Highways (DPWH) is fast-tracking the rehabilitation of the damaged sections of the Manila North Road (formerly MacArthur Highway) in Minalin town, this province.

DPWH Pampanga 1st District Engineer Almer Miranda said on Wednesday that the rehabilitation, reconstruction, and upgrading of the 1,642 linear-meter Minalin section of the Manila North Road is now halfway done.

“We have been under strict instruction from Regional Director Roseller Tolentino to exhaust all means to expedite our projects months before the onset of the rainy season,” Miranda said in an official social media post.

The national government has allotted some PHP91 million for the rehabilitation of the damaged sections of Manila North Road that is being implemented through the DPWH’s Asset Preservation Program.

Miranda said the implementation of the rehabilitation project funded under General Appropriations Act for the year 2020 began on Dec. 1, 2020.

Although the project was tagged as under “For Later Release,” he said the Pampanga 1st District Engineering Office immediately started the road rehabilitation project after the Department of Budget and Management released the funds, making it 73 percent complete as of May 25, 2021.

“We are doing our best to meet the July 2021 target to complete the road rehabilitation. Three years ago, in 2019, the average daily traffic along this section of the Manila North Road is at 50,000, and considering this volume of vehicles that surely increased in three years, it is expected that the condition of the road pavement had to take the toll,” Miranda added. (PNA)