PBBM To Filipinos Abroad: Exercise Your Right, Avail Of Online Voting

Ang mga Pilipinong nasa ibang bansa ay hinikayat ni Pangulong Marcos na gamitin ang kanilang karapatan sa pagboto sa pamamagitan ng Online Voting System.

DTI Chief: First Quarter GDP Growth Shows Resilient Philippine Economy

Ayon sa DTI, ang paglago ng GDP sa unang kwarter ng 2025 ay patunay ng katatagan ng ekonomiya ng Pilipinas sa harap ng mga pagsubok.

DAR Distributes PHP8.2 Million Equipment To Bukidnon Farmers’ Groups

DAR namahagi ng PHP8.2 milyong kagamitan sa 15 agrarian reform beneficiary organizations sa Bukidnon, pinatatag ang sektor ng agrikultura.

Iloilo City Launches 1st LGU-Led Nutrition Hub For Kids, Moms

Iloilo City inilunsad ang unang LGU-led Nutrition Hub para sa mga bata at mga ina. Ang Uswag Nutrition Center ay naglalayong magbigay ng masustansyang pagkain para sa lahat.

Suspension Lifted For P64-M Mati City Hall Project

Suspension Lifted For P64-M Mati City Hall Project

6
6

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The rehabilitated building of the Mati City Hall will finally be occupied within the month after Mayor Michelle Rabat lifted the suspension she earlier imposed on the project.

Rabat suspended all ongoing projects of the previous administration upon her assumption on June 30, 2019.

Rabat said she lifted the suspension on several of the projects that already undergone a forensic audit, including the PHP64.5 million City Hall building project.

The rehabilitation of the City Hall building was undertaken by Lotrim Construction, Inc. on Mar. 21, 2016 under the administration of then-Mayor Carlo Rabat.

Before the incumbent mayor’s assumption, the local government already paid the contractor PHP62.3 million.

In an Audit Observation Memorandum (AOM) released by the Commission on Audit on August 28, 2019, the agency noted that “bidding documents and all related documents forming part of the contract were not submitted to the COA Office contrary to the provisions of COA Circular No. 2009-001, particularly on the submission of contracts which must be within five working days from the execution.”

The COA recommended to the new mayor to “require the responsible officials/employees to immediately submit the bidding documents and the supporting documents for the payments to Lotrim Construction”.

Rabat said the contractor already met with local officials to complete the project.

Rabat also recently ordered the termination of the PHP25-million contract for the improvement of the FGR Park and Baywalk that was entered into by the previous administration for failure to utilize the amount within the prescribed period. (PNA)